Commercial Project
ECS carried out the re-design of the existing infrastructure, specifying eight new UPS units and a new generation control panel,,with an additional generator connection and the fitting of an upgraded distribution system.
The new data centre now also benefits from close control cooling plant and gas discharge system.
Project Overview | Data Centre development |
Key Aspects | UPS and standby generator |
Overall project value | £350,000 |
Client | Client Team |
ECS dealt directly with the client in relation to a complex logistics programming that allowed the existing data centre to operate normally, with no business interruption or reduction in capacity.
The entire project was undertaken in an ordered manner with close project management provided by ECS Consultants. This level of support enabled the client to grow in confidence as the various business critical switching operations were undertaken.