Commercial Project

Delta House, Manchester

This project involved the establishment of a new data mall to handle increased system capacity.

ECS carried out the re-design of the existing infrastructure, specifying eight new UPS units and a new generation control panel,,with an additional generator connection and the fitting of an upgraded distribution system.

The new data centre now also benefits from close control cooling plant and gas discharge system.

ECS logo
Project Overview Data Centre development
Key Aspects UPS and standby generator
Overall project value £350,000
Client Client Team

ECS dealt directly with the client in relation to a complex logistics programming that allowed the existing data centre to operate normally, with no business interruption or reduction in capacity.

The entire project was undertaken in an ordered manner with close project management provided by ECS Consultants. This level of support enabled the client to grow in confidence as the various business critical switching operations were undertaken.

Latest News

ECS projects beyond The Stockport Pyramid

23 Oct 2026

Read Article

Sustainable MEP Design for Logistics

02 Oct 2026

Read Article

We’re now CPD accredited!

21 Aug 2026

Read Article