Hurst Knoll Schools, Tameside

This project combined our practical approach to design with an ability to act as lead consultant, delivering a complex project within budget and strict logistical timeframes.

The rewire of this two form entry Primary and Nursery School had to be carried out during term time because the budget provision did not include for temporary accommodation and the School had no spare classrooms.

ECS set about the re-design, dovetailing with the logistical complications of the installation process. During a two week holiday period, a new sub-distribution system was installed with circulation spaces rewired.

During the following weeks, classrooms were rewired from Friday evening to Sunday afternoon. The late afternoon was given over for cleaning and replacing furniture.

ECS logo
Project Overview Electrical rewire
Key Aspects Lighting control
Overall project value £250,000
Client Tameside Metropolitan Borough Council

This plan was devised during detailed meetings with both the school and Local Authority. It met all of the needs necessary to provide an enhanced and safer environment and was delivered on time and within the Local Authority budget.

ECS carried out weekend project management to ensure project delivery within the very tight timescales.

Latest News

Business Fives

16 Feb 2024

Read Article

ECS Team Attends ASHRAE Winter Conference

02 Feb 2024

Read Article

Decarbonisation Education

04 Jan 2024

Read Article

The future lies with ECS…..

22 Dec 2023

Read Article

©2024 ECS Consultants | Website by Obi